The renovation of Harmon High School took place over the summer of 2004.
JPI's scope of work began June 1, 2204 and included:
Project coordination between the Architect, construction manager, JPI,
material suppliers and the various trades was crucial to the success of this
project.
![]() |
![]() |
![]() |
Work commenced on June 1, 2004 with the removal and replacement of approximately 5,300 square feet of existing monolithic glass. This glass was replaced with 1" insulated units, both tempered over tempered and tempered over Laminated safety glass. Measurement taken in advance insured that material arrived on site in a timely manner as work areas became available.