The renovation of Harmon High School took place over the summer of 2004.
JPI's scope of work began June 1, 2204 and included:
Project coordination between the Architect, construction manager, JPI,
material suppliers and the various trades was crucial to the success of this
project.
![]() |
![]() |
![]() |
Installation of the 44 custom pre glazed windows (approx. 5'-0" x 8 '-0") and 27 FRP Doors was completed in approximately 2-3 weeks. Pre measurement weeks in advance, along with communication and coordination with suppliers insured the installation was completed on schedule.
The custom skylight (approx. 78'-0" x 11'-0") a long lead time item, arrived as scheduled after the school year commenced. A four man work crew received and installed the new skylight and the work was completed in approximately 3 weeks.