"The organized preparation for this project assisted us in completing this job in a productive and timely manner. Working on this project definitely magnified our strength of working as a team, as many members of JPI had a hand in completing this job." - Dustin

Hickman Mills Schools
Nashua Elementary

The renovation of the Hickman Mills Schools took place over the summer of 2004. This project consisted of seven Elementary schools and four High Schools.

Prefabrication of the storefront frames made installation run smoothly. Field verification months before ensured a custom fit for each opening. Frames were shipped to jobsite ready for installation. In approximately 50 working days, with crews ranging from 4 to 8 workers, JPI replaced over 1000 windows and storefront systems and 7 entrances.