The renovation of the Hickman Mills Schools took place over the summer of 2004. This project consisted of seven Elementary schools and four High Schools.
![]() |
![]() |
![]() |
![]() |
![]() |
Prefabrication of the storefront frames made installation run smoothly. Field verification months before ensured a custom fit for each opening. Frames were shipped to jobsite ready for installation. In approximately 50 working days, with crews ranging from 4 to 8 workers, JPI replaced over 1000 windows and storefront systems and 7 entrances.